25 October 2026 — Carmen de la Legua, Callao, Peru. The TBM Micaela reached Carmen de la Legua on 22 October 2026, completing station excavation on the Lima Metro Line 2 project and its 8-station Line 4 branch, the report said. The Ministry of Transport and Communications (MTC) commissioned both lines and was represented at the breakthrough by Minister Angello Tangherlini; Peru’s President Keiko Fujimori attended the event, which the government described as completing station excavation for Line 2 and the branch. The article reports that Webuild and consortium partners carried out the tunnelling works, with two TBMs — Micaela and Delia — boring more than 20 km between them.
Project delivery remains staged. The system is a 35 km, 35-station scheme (Line 2: 27 km/27 stations; branch that will form Line 4: 8 km/8 stations). The concessionaire projects commercial operation of stage 1B in 2029, and stage 2 and the Line 4 branch in October 2030, according to the report. Civil-completion percentages cited by Ositrán and MTC include stage 1B at 96% average, stage 2 at 91%, and the Line 4 branch at 66%; Carmen de la Legua station was reported 56.12% complete overall and 82.73% for civil works on 23 October 2026. The reported total investment figure cited by Minister Tangherlini was about $5.35 billion, and President Fujimori cited approval of a supplementary credit of more than 8 billion soles that includes funding for Line 2.
Lead
25 October 2026 — Carmen de la Legua, Callao, Peru. TBM Micaela reached Carmen de la Legua on 22 October 2026, completing station excavation work on Lima Metro Line 2 and its 8-station Line 4 branch, according to the report. The Ministry of Transport and Communications (MTC) commissioned both lines and attended the arrival; Peru’s President Keiko Fujimori and Minister of Transport and Communications Angello Tangherlini were present. Webuild and its consortium partners carried out the tunnelling works, using two TBMs identified as Micaela and Delia, which the company said bored more than 20 km between them.
Project facts
- Project name: Lima Metro Line 2 and Line 4 branch
- Location: Lima metropolitan area and Callao, Peru (Carmen de la Legua station in Callao)
- Owner: Not publicly disclosed
- Commissioning authority: Ministry of Transport and Communications (MTC)
- Timing: TBM breakthrough at Carmen de la Legua on 22 October 2026; Micaela began operating 27 November 2022; concessionaire projects stage 1B commercial operation in 2029; stage 2 and Line 4 branch planned for October 2030 (reported)
- Scope: Total system 35 km and 35 stations. Line 2: 27 km, 27 stations, one depot. Line 4 branch: 8 km, 8 stations, second depot at Bocanegra. Stage definitions: stage 1A (five stations) in service; stage 1B (11 stations) and stage 2 (11 stations) remaining as reported
- Technical parameters: TBMs Micaela and Delia; Micaela excavated 11.3 km to date per MTC; Rímac River crossing of 136 m lined with 80 rings; Carmen de la Legua station civil works 82.73% and overall 56.12% complete on 23 October 2026 (MTC)
- Value and financing: Total investment put at about $5.35 billion by Minister Tangherlini (reported). President Fujimori cited a supplementary credit of more than 8 billion soles that includes funding for Line 2. Other financing details: Not publicly disclosed
Participants and responsibilities
- Commissioning authority / grantor: Ministry of Transport and Communications (MTC) — commissioned both Line 2 and the Line 4 branch; provided completion percentages and timeline positions (source: MTC; source confidence: official government release)
- Regulator / reporting body: Ositrán — provided tunnelling breakthrough dates and construction progress percentages and noted dismantling of TBM Delia (source: Ositrán updates; source confidence: official regulator release)
- Main tunnelling contractor / consortium: Webuild and consortium partners — performed TBM excavation; the company said TBMs Micaela and Delia bored more than 20 km between them and described Micaela’s arrival as the final breakthrough (source: Webuild statements reported by the article; source confidence: company announcement)
- Concessionaire: Not publicly disclosed by name; described in reporting as the concessionaire managing staged delivery and projecting operation dates (source: report; source confidence: secondary media)
- Political leadership: Peru President Keiko Fujimori and Transport Minister Angello Tangherlini — present at the breakthrough and cited investment and financing figures (source: government presence and statements reported; source confidence: official/government reporting)
- TBMs and worksites: TBM Micaela and TBM Delia — roles and tunnel segments reported (source: MTC, Ositrán, Webuild; source confidence: official/company/regulator reporting)
- Rolling stock, systems, operator, consultants, financiers: Not publicly disclosed
Contractor overview
- Webuild (and consortium partners) — role: tunnelling contractor; scope: operated TBMs Micaela and Delia to excavate Line 2 and the Line 4 branch tunnels; reported scale: TBMs bored more than 20 km between them; specific contract value: Not publicly disclosed; source confidence: company statement and regulator reporting.
- Other contractors (civil works, systems, electromechanical, concessionaire): Not publicly disclosed in the cited material; reported progress percentages for civil works and systems are attributed to MTC and Ositrán updates.
Commercial context
The reporting evidences staged delivery under a concessionaire model: five stations of stage 1A are already in service; stage 1B (11 stations) had averaged 96% civil-works completion and is reported by the concessionaire to target commercial operation in 2029. Stage 2 and the Line 4 branch are reported at 91% and 66% civil-completion respectively, with the concessionaire projecting October 2030 for commercial operation of stage 2 and the branch. Ositrán previously noted shifting schedule proposals and absence of a single agreed construction schedule between the MTC and the concessionaire; earlier regulator commentary in February reported alternative handover and indirect transfer options. Reported public financing comments include a ministerial investment estimate of about $5.35 billion and presidential reference to a supplementary credit of more than 8 billion soles that includes Line 2 funding. No first-party contract values, rolling-stock suppliers, or operator names were disclosed in the cited material.