PKP Intercity’s 15-year ED74 overhaul tender now closes to bids November 4
Article Summary
Source-basedBids in PKP Intercity’s ED74 overhaul tender, which covers three P4 maintenance campaigns on 14 electric trainsets over 15 years, are now due November 4 after four deadline extensions. Bidders have until 12:00 on November 4, and the offers are scheduled to be opened half an hour later. The original contract notice, published on August […] Сообщение PKP Intercity’s 15-year ED74 overhaul tender now closes to bids November 4 появились сначала на Railway Supply .
Full Article
Bids in PKP Intercity’s ED74 overhaul tender, which covers three P4 maintenance campaigns on 14 electric trainsets over 15 years, are now due November 4 after four deadline extensions.
Bidders have until 12:00 on November 4, and the offers are scheduled to be opened half an hour later. The original contract notice, published on August 28, 2026, set October 1 as the closing date. Change notices then moved it to October 13, October 20 and October 27, and the latest change notice, published on October 26, set the current date. Offers must remain valid until March 3, 2027. The change notices list the old and new dates but give no reason for the postponements.
A separate change notice published on October 7 lowered the security requirements. The bid security was cut from PLN 3.4 million to PLN 1.7 million, and the performance guarantee the winning bidder must provide before signing fell from 5% to 3% of the total gross price.
ED74 overhaul tender: bid deadline and terms by notice, 2026Notice published
Bid deadline (12:00)
Bids valid until
What changed
August 28, 2026
October 1, 2026
January 28, 2027
Original contract notice
September 28, 2026
October 13, 2026
February 9, 2027
Deadline extended
October 7, 2026
October 13, 2026
No change listed
Bid security cut from PLN 3.4 million to PLN 1.7 million; performance guarantee lowered from 5% to 3% of the total gross price
October 13, 2026
October 20, 2026
February 16, 2027
Deadline extended
October 20, 2026
October 27, 2026
February 23, 2027
Deadline extended
October 26, 2026
November 4, 2026
March 3, 2027
Deadline extended
The bid deadline has moved four times, from October 1 to November 4, 2026. Bids are opened at 12:30 on the deadline day. Dates are taken from the six versions of the contract notice published by PKP Intercity in the EU tenders database (TED), notices 596153-2026 to 739552-2026.
Award criteria and contract terms
The procurement runs as an open procedure under Poland’s public procurement act of September 11, 2019, and is classified as a sectoral contract. Gross price carries 80 points. The remaining 20 go to the time needed to repair one vehicle (10 points), the start date of repairs in the first campaign (5 points) and the warranty period for trouble-free operation of the whole vehicle after repair (5 points).
The contract allows no renewals and is not a framework agreement. Bids are filed through PKP Intercity’s online procurement platform, with detailed requirements set out in the tender documentation. The published notice data does not include an estimated contract value.
ED74 fleet after P5 modernization
The 14 ED74 units in the tender went through fifth-level (P5) periodic repairs combined with modernization under a PLN 274.8 million gross contract that PKP Intercity signed in June 2019 with a consortium of ZNTK Mińsk Mazowiecki and Pesa Bydgoszcz. The first modernized trains began carrying passengers in the second half of 2021.
On May 31, 2023, PKP Intercity announced that the last of the 14 modernized ED74 units had joined its fleet. After the work, the trains offer air conditioning, Wi-Fi, a power outlet at every seat, mobile signal boosters, space for bicycles and facilities for passengers with disabilities.