On 8 October 2026 in the Seattle region, Sound Transit staff brought Motion No. M2026-41 to the System Expansion Committee seeking authority to raise the Lynnwood Link closeout contingency ceiling to $70,203,671 from the $30 million ceiling approved in 2024–25. Staff asked the committee to forward the motion to the full board for final action scheduled on 22 October 2026. The requested increase would be an internal reallocation within the Lynnwood Link Extension baseline budget of $2,767,734,000 and, according to the staff report, would commit no new funds.
The agency presentation and staff materials show authorized commitments at $2,727,530,000 and indicate that adding the requested $40,203,671 (rounded in the presentation to $40,204,000) would equal the project’s full baseline budget. The staff report and presentation identify remaining closeout tasks including safety certification, permit conditions, property dispositions and long-term agreements. The presentation shows the punch list at 98% complete, permits at 93% complete and property dispositions at 59% complete. The request would permit the chief executive officer to raise contract and agreement amounts as needed from existing budget lines for final design, construction services, third-party and construction phases; staff must report use of the contingency and recipient contracts by Q4 2027. Source: Railway Supply reporting on Sound Transit staff materials and motions.
Lead
On 8 October 2026, Sound Transit staff presented Motion No. M2026-41 to the System Expansion Committee in the Seattle region asking the committee to forward a board motion to raise the Lynnwood Link closeout contingency ceiling to $70,203,671. The full Sound Transit Board is scheduled to take final action on 22 October 2026. The request would increase the cumulative contingency cap above the $30 million level set by prior board actions in 2024 and 2025.
Verified facts
Sound Transit staff want the board to add $40,203,671 to the cumulative closeout contingency cap for the Lynnwood Link Extension, bringing the ceiling to $70,203,671. The presentation rounded the requested addition to $40,204,000 when illustrating budget impact. The requested authority would be drawn from the Lynnwood Link Extension’s existing baseline budget of $2,767,734,000; the staff report states the action commits no new funds and allows the chief executive officer to raise contract and agreement amounts as needed from existing budget lines. The committee presentation shows authorized commitments at $2,727,530,000; adding the requested $40,203,671 would equal the full baseline budget.
Sound Transit historical context disclosed in staff materials notes the board first allowed up to $15 million in cumulative contingency increases under Motion No. M2024-16 in March 2024. A March 2025 staff memo reported use of contingency totaling $9,165,886 (with the memo text giving $9,185,886 but its table summing to $9,165,886), primarily for extending design services during construction. Motion No. M2025-19 doubled the ceiling to $30 million. The new request would more than double that $30 million ceiling.
Organizations and responsibilities
Sound Transit: the agency seeking board authority to increase the cumulative contingency ceiling and to permit the chief executive officer to adjust contract and agreement amounts within the baseline budget. The staff report and presentation are Sound Transit materials. The System Expansion Committee and the Sound Transit Board are the decision-making bodies scheduled to review and act on Motion No. M2026-41.
HNTB-Jacobs Trusted Design Partners: named in the staff presentation as included among design services eligible for the additional authority. Stacy & Witbeck – Kiewit – Hoffman joint venture: identified as the heavy civil contractor for the Northgate Station to NE 200th Street section and listed among contracts eligible for the authority. Construction management consultants PGH Wong Engineering and Northwest Transit Systems Partners: listed as eligible recipients of the additional authority. WSDOT: identified as a jurisdiction crossed by the route and as a party with task orders covering surplus property and landscape oversight during the plant establishment period. Property consultants CLS, David Evans and Associates and Furtado: named among real property consultants eligible for additional authority. Long-term construction services and permit review agreements with the cities of Seattle and Shoreline are also included. All roles and listings are taken from the Sound Transit staff presentation and report.
Operational and commercial context
The staff report says closing out the ST2 lines has become an agency priority and that general contractor/construction manager contracts are being extended to cover closeout work. The presentation states the punch list is 98% complete, permits 93% complete and property dispositions 59% complete. Staff list uses for the additional contingency including safety certification, changes requested by the agency, changes required by authorities having jurisdiction, permit conditions and property transfers, and follow-on work involving Sound Transit, the cities and WSDOT. The presentation shows the request would allow additional contract and agreement authority in final design, construction services, third-party and construction phases; staff must provide the board a full accounting of contingency use and the contracts it funded no later than Q4 2027.
The staff materials compare Lynnwood Link contingency levels with other recent Sound Transit extensions: Federal Way Link Extension cumulative ceiling increases reached an additional $50 million to $110 million in December 2025 (on top of $60 million authorized earlier under M2025-10) within a baseline budget of $2,451,535,000; East Link’s ceiling reached $110 million in January 2026 after a $60 million increase. The staff presentation reports that, if approved, the Lynnwood request would represent about 2.5% of the Lynnwood baseline budget, compared with about 4.5% for Federal Way, based on the figures cited in the staff materials.
Sources
https://www.railway.supply/sound-transit-seeks-70-2m-lynnwood-link-closeout-cap-up-from-30m/ — Railway Supply
Disclosure